The project - to replace current drainages pipes (24 - 36") with larger drainage pipes (36 - 72") - is progressing as planned. With the completion of the outlets at Mesquite near the middle school and drainage pipes along Mesquite Dr., the Mesquite/Green Fields Intersection, and now Sleepy Hollow, the project will now enter the last phase with construction along Green Fields. Beginning Monday, April 5th, the eastbound lane of Greenfields will be closed and detoured via Hidden Creek. Affected homeowners will be notified via flyers posted to individual homes. The project, which was originally estimated for a May 2021 completion, is now estimated, weather permitting, for completion June 2021.
top of page
bottom of page